Report finds that the US lacks funds to complete the first phase of air-traffic control reforms.

According to a government report released on Sunday, the Federal 'Aviation Administration' needs additional funding from Congress in order to complete phase one of a $10.6-billion air traffic control plan. They also underestimated the total cost of operating the new system.

The Government Accountability Office stated that the FAA did not have a full assessment of the costs associated with operating the new system, nor had it set out a schedule to complete the reforms.

The GAO report stated that "the FAA buys delivery speed by risking cost uncertainty and disruptions." It added, "these risks increase FAA's likelihood of repeating past cost overruns and performance targets."

Congress approved $9 billion in the first phase of ATC reforms. GAO reported that the FAA is also using $1 billion of its budget for this year and requires another $574 millions. GAO reported that the cost of telecommunications upgrade has risen from $4.75 billion up to $5.91billion.

FAA Administrator Bryan Bedford will?testify before Congress on Tuesday? about the efforts and plan to start deploying a program based on software to try to prevent flight delays.

The GAO reported that the FAA is implementing over 11,000 projects as part of phase one, a $10.6 billion plan for reform.

In a letter sent to the GAO, the FAA stated that it was committed to using the best practices in order to oversee the project which it said "remains on plan" including 95% of the specific tasks.

The FAA’s current air traffic control system is "severely out-of-date, unreliable, and not sustainable." The aging, unreliable technology is a major contributor to the increase in aviation accidents.

The biggest risk is replacing air traffic control towers voice switches because of their size and the airspace they cover, the technology used and the need to operate both new and old switches at the same time.

The GAO stated that the FAA published its first comprehensive plan to improve air traffic control services in 1982. Since then, it has suffered from a number of cost overruns and delays and delivered limited results.

In December, the FAA awarded a $1.5billion contract to Peraton (owned by Veritas Capital) for overseeing modernization efforts.

(source: Reuters)