Sources say that the $30 billion Morocco-Germany power cable has been stalled due to governance differences.

Four sources claim that a $30 billion project, which would provide Germany with renewable energy from Morocco via the longest intercontinental undersea power link in the world, is currently being delayed by disagreements about structure and guarantees.

Sila Atlantik is a project that aims to link Morocco and Germany through two subsea cables capable of delivering up to 5% the annual German electricity demand.

According to project developers, the cables would be 4,800 km long (2,892 meters) and fed by solar and wind power installations up to 15 gigawatts in Morocco. The total infrastructure costs around $30 billion.

European countries want to increase the number of such connections in order to reduce their dependence on fossil fuels and improve energy security. Sila 'Atlantik was created by a German firm for this project after a similar proposal to build a renewable electricity link between Morocco and the UK called Xlinks collapsed a year ago.

Two Moroccan and two German sources with knowledge of the issue have said that the project has now hit a snag, as the Moroccan authorities are insisting on a formal intergovernmental agreement to be endorsed by Berlin in order to guarantee long-term support from the state.

The sources, who requested anonymity because they weren't authorised to publicly speak on the issue, said that Morocco would also like the connection to be able to send electricity both ways.

One German source stated that a two-way link would be technically feasible but more expensive economically.

A senior official from the region said that Moroccan authorities have promised to dedicate around 150,000 hectares in southern Guelmim - Oued Noun to the Xlinks Project, but they haven't yet approved the same allocation to Sila Atlantik.

Sila Atlantik didn't answer specific questions regarding the project, but stated that it was "progressing according to its technical, financial, commercial and regulatory roadmap."

The company responded in an email that "the project continues to evaluate the technical and regulatory alternatives that will best support its long-term growth."

The Moroccan Energy Ministry didn't reply to questions but stated 'by email' that "regional Integration is a key component of Morocco's Energy Transition Strategy" and emphasized plans to strengthen electricity links with European partners.

A second Morocco-Spain connection with a capacity of 700 megawatts is being planned. Meanwhile, a Morocco-Portugal link currently under study could require investment up to 735 million euros ($838 million). According to a document from the electricity utility ONEE seen by, a second Morocco-Spain link with a capacity of 700 Megawatts is planned. A Morocco-Portugal connection currently under study may require an investment of as much as 735 Million Euros ($838 Million). According to a document from the electricity utility ONEE, a connection with France is also planned.

Morocco and Portugal plan to submit their proposed electricity link to the European Union T-MED Programme, which aims at mobilising up to 25 billion euro in investment to support renewable energy cooperation and cross border electricity infrastructure. (Reporting and Editing by Ahmed El Jechtimi: Editing By Sharon Singleton).

(source: Reuters)