Golden Pass LNG asks US regulator for 3-year extension to complete building

The developer of a Texas melted gas export task on Wednesday asked U.S. regulators for a threeyear extension to total building of the $10 billion Golden Pass LNG task, mentioning scheduling unpredictabilities.

Golden Pass LNG, a joint endeavor of QatarEnergy and Exxon Mobil building an 18 million metric heap per annual LNG export project on the Texas coast, wrote that a. change in primary professionals needs an extension until. November, 2029.

Exxon and QatarEnergy this month said the job start-up. would be delayed up until late next year. The present approval. ends in November 2026 and the demand indicates a later on. start-up.

The business's objective is to produce first LNG around the end. of 2025 with industrial operations following afterwards, a. Golden Pass LNG representative said. The extensions we have. requested integrate in time for contingencies.

QatarEnergy owns 70% of the joint venture and Exxon the. rest.

The extra time will enable the rehiring and. remobilization of over 4,000 proficient workers and attend to. prospective uncertainties such as serious weather or cyclone. delays when it might not be safe to have crews on site, Golden. Pass LNG composed the Federal Energy Regulatory Commission.

In May, Zachry Industrial, which was the primary specialist. for the task, declared insolvency after a disagreement over $2.4. billion in expense overruns. Golden Pass LNG consequently named. CB&I, an unit of McDermott International, as lead. contractor.

Golden Pass LNG is seeking the extra three-year duration. under a FERC arrangement that enables an extension if a company can. reveal it made great faith efforts to finish a job on time,. it said in a letter to FERC.

Building of the very first gas-processing unit is. approximately 83% complete, and the 2nd and third processing. units are 46% and 31% complete, respectively, the FERC filing. stated.

(source: Reuters)