Latest News

Document shows that the second Venture Global LNG plant is running over budget.

Financial documents prepared for Venture Global LNG’s initial public offering (IPO) of shares show that the second liquefied gas export plant currently under construction in Louisiana is 2,35 billion dollars over budget. Costs could continue to rise.

Inflationary pressures and construction costs were blamed by the fast-growing LNG company to maintain schedule. Documents viewed by us show that the Plaquemines facility's final cost was estimated to be between $21 and $22 billion.

No immediate comment was made by the company.

In the coming weeks, it is likely that the 20 million metric ton per annum (MTPA), export facility will begin producing supercooled gas. This could be the first of two U.S. LNG facilities to begin operations in this year.

The cost of labor, steel, and processing equipment has caused U.S. LNG project developers to suffer budget overruns, and in some cases they are running behind schedule.

Zachry Holdings, the lead contractor in the Golden Pass LNG joint venture between QatarEnergy & Exxon Mobil, filed for bankruptcy earlier this year and left the project. The project was over $2 billion behind budget and one year behind schedule. The project could start operations as early as 2026 or late in 2019.

The preliminary IPO documents show that Venture Global has already covered the cost overrun of $2.35 billion and believes it will have sufficient cash, borrowing capability and "access" to commissioning cargoes to cover any future increases.

Venture Global LNG CEO Mike Sabel said in an interview at the end of last year that Plaquemines would have a commissioning period similar to its Calcasieu Pass LNG plant, and contract customers could receive their first LNG cargoes as early as 2026.

The company was founded 11 years ago by a lawyer in energy and an investment banker. It has rapidly become a major LNG exporter, competing with larger rivals Cheniere Energy and Freeport LNG.

CONTRACT DISPUTES

Documents show that Venture Global's Calcasieu Pass 10 MTPA plant is expected to cost $9.8 Billion, including repairs to a faulty heat-recovery steam generator which delayed commercial operation.

According to its consolidated financial statements, Venture Global will spend an additional $343 million on repairs.

It could be costing the company hundreds of millions in disputes with BP Shell Edison and Orlen over the startup of its plant.

Documents show that Venture Global has been commissioning Calcasieu pass since March 2022. It has sold its commissioning goods on the spot market, earning an operating profit of $8.4 Billion between March 2022 to December 2023.

(source: Reuters)