Latest News

U.S. court overturns FERC's authorization for NextDecade's Rio Grande project

A U.S. court has overturned the Federal Energy Regulatory Commission's (FERC) authorization for NextDecade's Rio Grande LNG task for not releasing a. additional environmental effect declaration, the business stated on. Tuesday.

The center has actually remained in development for numerous years,. suffering duplicated hold-ups, and phase 1 is now anticipated to reach. conclusion by early 2029 at an expected expense of about $18. billion.

NextDecade said it was disappointed in the court's choice. and disagrees with its conclusions.

At this time, building continues the very first three. liquefaction trains and associated facilities (Phase 1) the. company stated, including it is evaluating the impact of the court's. decision on the timing of a positive final investment decision. ( FID) on Train 4.

Earlier this year, Abu Dhabi National Oil Business (ADNOC). got an 11.7% stake in phase 1 of the task and NextDecade. signed a non-binding contract with Saudi Aramco to. supply 1.2 million tonnes per annum (MTPA) of LNG for twenty years.

NextDecade was preparing to start the construction of the. 4th liquefaction train in the 2nd half of 2024 after the. FID.

(source: Reuters)